Build Update: January 09-14, 2017

Posted by Habitat Admin on Jan 9, 2017 4:48:00 PM

january-9-build-update.jpg

Pineridge Place, Calgary

Pineridge development is a new project that is located in the northeast Calgary community of Pineridgewill. The project will consist of six four‐plexes. Currently we have finished two four-plexes, and another two are being under construction.

Each unit will be approximately 1,030 sq. ft., with three bedrooms and one bath on the second floor, a half‐bath on the main level as well as kitchen and living spaces. The homes will be in close proximity to the Peter Lougheed hospital, Sunridge shopping mall, schools, services and public transportation. The homes will be built using energy saving building practices to an equivalent of a Build Green Gold level and thus reducing overall costs for utilities and water.

Pineridge plan

The construction process is going pretty fast for both buildings Building D and Building C.

Building D is almost complete. We are doing some painting and then waiting for appliances to arrive.

progress on Pineridge building D

Building C is currently having the roof installed and trades are starting on it as well.

installing windows and roofing on building C

Our need for volunteers is minimal until the roof is on, and the trades are finished – cold weather has been slowing the work down.

Bowness, Calgary

Bowness plan

Bowness development an exciting project that is located in the northwest Calgary community of Bowness. The project will consist of one six‐plex and expected to be finished later this year.

Each unit will be approximately 1,000 sq. ft., with three bedrooms. The units will be in close proximity to public transportation and parkways. All units will be built using energy saving building practices to an equivalent of a Build Green Gold level and thus reducing overall costs for utilities and water.

  • We have finished framing on the main floor and expecting to start framing decks this week.
  • Most of the work will be focused on exterior and interior framing, and flooring. 

Bowness framing progress

Topics: Build Update